We’re investing now to create a strong electricity network in Rolleston.
Rolleston has quickly become a go-to area for people to live, work and play. This rapid growth has meant we’re strengthening our network in the area.
We've nearly completed work on the new West Rolleston Zone substation on Burnham School Road.
In 2024 and earlier this year we also completed work to install new underground power cables to connect the existing substation at the corner of Dunns Crossing Road to the new West Rolleston substation on Burnham School Road.
Between 15 September - 5 October 2025, we'll be working on Burnham School Road to install an 11kV underground power cable. Ahead of this cable work, on Monday 8 September our crew will be onsite completing investigation work. To do this work safely, a shoulder closure will be in place. Please follow all signs and instructions from our crew
Where we're working We've been working to install the new underground power cables in three stages - see map below. We've completed stages one and two, and we'll shortly start working on the last stage of work on Burnham School Road.
Stage one: Completed
Install an 11kV underground cable on Dunns Crossing Road from Burnham School Road to Brookside Road.
Stage two: Completed
Install cable ducting for a 66kV underground power cable from the current Rolleston Substation to the new West Rolleston Substation site on Burnham School Road (across from West Rolleston Primary School).
Install an 11kV underground cable parallel to the ducting.
Stage three: 15 September - 5 October 2025
Install an 11kV underground cable in the berm of Burnham School Road to the intersection of Dunns Crossing Road.
Hours of work
Our crew will generally be working between the hours 7am - 6pm between Monday - Friday. Some weekend work may be needed at times.
How we install underground power cables:
Establishment of the traffic management on site.
Milling of the pavement surface.
Exposure of existing services using hydro excavation.
Digging the trench.
Placing and compacting dust in the base of the trench.
Laying cable will in the trench.
Placing and compacting dust around and on top of the cable.
Placing a Mag Slab (cable cover) on top of the dust.
The trench will be filled and compacted in layers.
Reinstatement of the pavement surface.
Disestablishment of the traffic management.
Parking
There will be no on-street parking available where we are working.
Construction of the West Rolleston Zone Substation
We've started construction of the new West Rolleston zone substation on Burnham School Road to increase the capacity of our power network in Rolleston.
Construction of the West Rolleston Zone Substation is underway with the civil works completed. All work on the substation is expected to be completed by mid 2026.
Most of this work should be contained within the worksite. At times, traffic management may be in place. Please follow all signs and instruction from our crew.
We’re investing now to create a strong electricity network in Rolleston.
Rolleston has quickly become a go-to area for people to live, work and play. This rapid growth has meant we’re strengthening our network in the area.
We've nearly completed work on the new West Rolleston Zone substation on Burnham School Road.
In 2024 and earlier this year we also completed work to install new underground power cables to connect the existing substation at the corner of Dunns Crossing Road to the new West Rolleston substation on Burnham School Road.
Between 15 September - 5 October 2025, we'll be working on Burnham School Road to install an 11kV underground power cable. Ahead of this cable work, on Monday 8 September our crew will be onsite completing investigation work. To do this work safely, a shoulder closure will be in place. Please follow all signs and instructions from our crew
Where we're working We've been working to install the new underground power cables in three stages - see map below. We've completed stages one and two, and we'll shortly start working on the last stage of work on Burnham School Road.
Stage one: Completed
Install an 11kV underground cable on Dunns Crossing Road from Burnham School Road to Brookside Road.
Stage two: Completed
Install cable ducting for a 66kV underground power cable from the current Rolleston Substation to the new West Rolleston Substation site on Burnham School Road (across from West Rolleston Primary School).
Install an 11kV underground cable parallel to the ducting.
Stage three: 15 September - 5 October 2025
Install an 11kV underground cable in the berm of Burnham School Road to the intersection of Dunns Crossing Road.
Hours of work
Our crew will generally be working between the hours 7am - 6pm between Monday - Friday. Some weekend work may be needed at times.
How we install underground power cables:
Establishment of the traffic management on site.
Milling of the pavement surface.
Exposure of existing services using hydro excavation.
Digging the trench.
Placing and compacting dust in the base of the trench.
Laying cable will in the trench.
Placing and compacting dust around and on top of the cable.
Placing a Mag Slab (cable cover) on top of the dust.
The trench will be filled and compacted in layers.
Reinstatement of the pavement surface.
Disestablishment of the traffic management.
Parking
There will be no on-street parking available where we are working.
Construction of the West Rolleston Zone Substation
We've started construction of the new West Rolleston zone substation on Burnham School Road to increase the capacity of our power network in Rolleston.
Construction of the West Rolleston Zone Substation is underway with the civil works completed. All work on the substation is expected to be completed by mid 2026.
Most of this work should be contained within the worksite. At times, traffic management may be in place. Please follow all signs and instruction from our crew.
Page last updated: 10 Sep 2025, 02:23 PM
Upcoming work
Between 15 September - 5 October, we'll be working to install an 11kV underground power cable in the berm on Burnham School Road.
To safely install the cable:
A shoulder closure will be in place along Burnham School Road opposite West Rolleston Primary School.
At times, stop/go traffic management may be in place.