Contractor installing a new 66kV cable in an open trench

You are here:

  • Home
  • Bromley to Milton power cable

Photos

New 66kV power cable
previous next
The new underground power cable is delivered to site on large drums. Each drum is 4.5m in diameter and each weighs around 27 tons. There are 27 drums of cable required for the new circuit from Bromley Substation to Milton Substation - three cables per trench. The new cable is supplied by Prysmian Group and takes around 12 months to procure and manufacture. This is the largest physical cable installed by Orion on its network.
Milling the road's surface
An installed cable duct
Crew installing cable ducts in a trench on Brougham Street
Laying new cables
New 66kV power cable
Dewatering spears installed in St Johns Street